Orsted books new losses, flags delay at US offshore wind project



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 5-Orsted books new losses, flags delay at US offshore wind project</title></head><body>

Q2 EBITDA up 59%, beats expectations

Books impairments of U.S. project delay

Keeps full-year profit forecast, says will lower investments

Shares end down 7%

Adds details on site of soil contamination, background on U.S. offshore wind

By Jacob Gronholt-Pedersen

COPENHAGEN, Aug 15 (Reuters) -Renewable energy group Orsted ORSTED.CO booked 3.9 billion Danish crowns ($575 million) in impairment losses in the second quarter, due partly to a delay in construction of a major U.S. offshore wind project, sending its shares down as much as9% on Thursday.

The world's biggest offshore wind developer pushed back the start of commercial operations at its 704 megawatt (MW) Revolution Wind project off Rhode Island and Connecticut to 2026 from 2025, it said in its quarterly results statement.

The announcement was the latest blow to the fledgling U.S. offshore wind industry, which is a major part of President Joe Biden's climate change agenda buthas been struggling with soaring costs.

In the last month alone, U.S. officials have cancelled a planned Gulf of Mexico offshore wind auction due to lacklustre industry demand, and construction on the nation's first major project was halted due to a shattered turbine blade that sent pieces of fiberglass washing up on nearby beaches.

Orsted's impairment losses also related to its Ocean Wind project in the United States whose development it halted last year, an increase in U.S. interest rates, and its decision to cease development of its green e-methanol FlagshipOne project, which was due to open in Sweden next year.

Shares in Orsted, once a green investor favourite, ended down7.2%, having fallen as much as 9.3% earlier. They remain at less than one-third of their value since peaking in early 2021.

The company last year found itself at the centre of a perfect storm of rising inflation, higher interest rates and supply chain delays, forcing it to cancel offshore projects in the United States, and related impairments surged above $4 billion.

In February, it trimmed its investment and capacity targets and paused dividend payouts following a strategic review of its business.


'FRUSTRATING AND UNSATISFACTORY'

The delay at Revolution Wind, which Orsted is developing in partnership with Eversource Energy ES.N, was due to soil contamination at an onshore transformer station.

The onshore facilities are being developed on the site of a naval air station that was decomissioned in the 1970s. The land includes buried waste from the demolished former facility, according to project planning documents filed with the federal government.

"This is not supply chain related. It is related to a specific challenge, which of course is frustrating and unsatisfactory," CEO Mads Nipper told journalists on a call, adding that offshore installation was going according to plan.

Impairment losses related to the project alone amounted to 2.1 billion crowns.

Still, the company beat analyst expectations with a 59% rise in second-quarter profit before interest, tax, depreciation and amortisation and excluding new partnerships of 5.27 billion Danish crowns.

That topped an average forecast of 4.41 billion crowns in a poll of analysts provided by Orsted.

Orsted kept its full-year profit forecast unchanged, but said it would lower investments this year.

Orsted said ithalted FlagshipOne, which was the largest e-methanol project under construction in Europe, because the green fuels market was developing slower than expected.

"We have decided to de-prioritize our green fuels business and focus our efforts on renewable hydrogen in northern Europe which is closer to our strategic core," Nipper said.


($1 = 6.7768 Danish crowns)



Reporting by Jacob Gronholt-Pedersen and Nichola Groom; editing by Terje Solsvik, Emelia Sithole-Matarise and Leslie Adler

</body></html>

免责声明: XM Group仅提供在线交易平台的执行服务和访问权限,并允许个人查看和/或使用网站或网站所提供的内容,但无意进行任何更改或扩展,也不会更改或扩展其服务和访问权限。所有访问和使用权限,将受下列条款与条例约束:(i) 条款与条例;(ii) 风险提示;以及(iii) 完整免责声明。请注意,网站所提供的所有讯息,仅限一般资讯用途。此外,XM所有在线交易平台的内容并不构成,也不能被用于任何未经授权的金融市场交易邀约和/或邀请。金融市场交易对于您的投资资本含有重大风险。

所有在线交易平台所发布的资料,仅适用于教育/资讯类用途,不包含也不应被视为用于金融、投资税或交易相关咨询和建议,或是交易价格纪录,或是任何金融商品或非应邀途径的金融相关优惠的交易邀约或邀请。

本网站上由XM和第三方供应商所提供的所有内容,包括意见、新闻、研究、分析、价格、其他资讯和第三方网站链接,皆保持不变,并作为一般市场评论所提供,而非投资性建议。所有在线交易平台所发布的资料,仅适用于教育/资讯类用途,不包含也不应被视为适用于金融、投资税或交易相关咨询和建议,或是交易价格纪录,或是任何金融商品或非应邀途径的金融相关优惠的交易邀约或邀请。请确保您已阅读并完全理解,XM非独立投资研究提示和风险提示相关资讯,更多详情请点击 这里

风险提示: 您的资金存在风险。杠杆商品并不适合所有客户。请详细阅读我们的风险声明